The Challenge

DSV required a base build of their new HP2 distribution centre in Thrapston, Kettering. This was needed to complete fit out works on schedule by July 2013.

The Solution

CS2 acted in a project monitoring role for DSV. Initially, CS2 conducted an audit of the developer’s base specification; negotiating an agreement of the specification, a suite of variations and access to commence DSV’s fit out prior to project completion, by taking a collaborative approach. CS2’s expertise resulted in the base build being completed on budget and 1 week ahead of programme. Subsequently, the fit out works were also completed to programme and within budget.

Project Manager

Andrew MatherManaging Director

CS2 ensure we are getting the building we require for the right cost and built to the spec that has been agreed with the developer. They look after our interests and make sure we get good value for money.

DSV Solutions