POUNDLAND DISTRIBUTION CENTRE, HARLOW
Project Value
£1.7m
Services Used
- Project Management
- Cost Consultancy
The Challenge
CS2 client Poundland required a new 24,000sqft chill store within their existing distribution centre. This was to assist with the roll out of its chilled and frozen food range across 500 of its stores.
CS2 acted as Project Manager and Cost Consultant for the delivery of the new chill store, which was completed whilst the existing DC remained fully operational.
CS2 provided feasibility options for different locations of the new chill facility within the existing DC. Existing spatial and power supply capacity to the site was limited and this played a limiting factor in the overall design. Our specialist team also provided co-ordination of the wider design team.
The Solution
Positive Outcomes for the client:
- New energy efficient 24,000sqft chill store within existing distribution centre
- Assisting with the roll out of ‘Project Diamond Ice’ across 500 stores
- Fully operational within 14-weeks of commencing works on site